Plate Heath Exchangers & Coolers
Those thermogram’s
illustrate the scale and deposit in Heat Exchanger’s effecting
the efficiency and function of the exchanger.
Separator Solids Level - Interface
IR Vision determine the level of solids in all type of vessels provided
that there is no lagging on the vessel. Modifications can easily be
made to accommodate for a survey by cutting out a strip approx. 35 cm.
wide from the lagging 90° up the side of the vessel from the bottom.
Produced
Water Lines
Produced Water equipment run a high risk of Scale fall out. The build
up often happen very quickly and will create a problem for the
production rate if the lines are unable to handle the amount of water
present in the production.
As water injection become more and more used the rate of produced water
increase
sharply and the produced water lines have a more critical role in the
system.
Some of the largest Scale build up have been found in produced water
systems and it is also here where a more frequent reoccurrence take
place.
MIC
Inspections (Bio Film)
A new inspection method developed through a major oil company.
Detecting Bio Film which deteriorate the carbon steel at sometimes an
alarming rate of speed. When the problem was identified in the oil
lines, we conducted a survey through the whole system identifying from
very small levels of MIC up to the larger levels. This inspection is
extremely hard to conduct and require a very good knowledge of the
system inspected as well as a long experience within petrochemical
process inspections. We are here working on the limit of what is
possible to achieve, and within very small temp. differences.